Legal Notices
NOTICE OF ACCEPTANCE
AND
FINAL PAYMENT TO CONTRACTOR
FOR
THAW WELLS 5 AND 6
Notice is hereby given that the Teton Conservation District has accepted, as completed
according to the plans, specifications and rules governing the same, the work performed
under that contract dated April 16, 2025 between the Teton Conservation District and
Weber Water and Well, LLC, the Contractor; that work under said contract, known as
Thaw Wells 5 and 6, is complete, and the Contractor is entitled to final payment. Notice
is further given that subsequent to the forty-first (41st) day after the first publication of this
notice, to wit, May 26, 2026, the Teton Conservation District will pay to said Contractor
the full amount under the contract.
……………………………………………………………………………………………
Publish April 15 and 22, 2026
